Guide · Permits

Permits & engineering for Toronto underpinning

Lowering a foundation changes how the house carries load. The City reviews engineered drawings before the first pin is opened, and inspects at defined stages afterwards.

Reviewed by Jamie Alves-Ferreira, President · Updated

Foundation Kings foreman in a branded sweater preparing materials for basement underpinning
Moore Park · preparing the next pour

What the City of Toronto reviews

A building permit application for underpinning is built around a set of stamped structural drawings showing the existing foundation, the new footing depth, pin sizes, the sequence and any temporary support. Architectural drawings are added when the layout, a bathroom, a walkout or a secondary suite is part of the scope.

Scopes that add their own review

  • Plumbing. New drains, a bathroom rough-in or a backwater valve.
  • Secondary suites. Ceiling height, egress, fire separation and sound requirements.
  • Walkouts. Exterior excavation, retaining walls, and sometimes zoning or ravine considerations.

Inspections during the work

Inspections are called at the stages the permit lists, typically before concrete is placed in the footings and pins, and at drainage and final stages. A contractor who manages inspections as part of the schedule keeps the project moving.

The paperwork you should finish with

  1. The issued building permit and approved drawings.
  2. Inspection records showing each stage passed.
  3. Engineer's field reviews, where required.
  4. Warranty and scope documentation from your contractor.

Primary sources

Requirements change. Always confirm against the City of Toronto directly:

The Foundation Kings coordinate engineering, drawings and permit submission as part of every turnkey project.

From our job sites

Underpinning pins numbered in orange paint along a basement wall to show the excavation sequence
East York · pins numbered in their dig sequence
Steel shoring posts supporting a basement during underpinning
Moore Park · temporary shoring in place
Timber formwork and shoring for an underpinning pin
Moore Park · formwork ready for concrete

Questions homeowners ask

Do I need a permit for underpinning in Toronto?
Yes. Underpinning changes how the house carries load, so the City of Toronto requires a building permit based on engineered drawings before work starts, with inspections at defined stages.
What happens if underpinning is done without a permit?
Unpermitted structural work can be ordered opened up for inspection, can complicate insurance claims, and is routinely flagged when the house is sold.
How long does a Toronto underpinning permit take?
It depends on the City’s current review queue and how complete the submission is. A complete, well-coordinated drawing set is the single biggest factor you can control.

Plan the next step

Talk to the team that does the work

Every enquiry on this site goes directly to The Foundation Kings. Book a free on-site assessment and get measurements, method and scope reviewed in person.

5.0 90 Google reviews

The Foundation Kings · WSIB insured · Engineered & permitted work

Call The Foundation Kings ·Call now · 416-565-5464